To bid electrical jobs, work out five numbers in order: materials, labor hours, loaded labor cost, overhead and profit, then put them in a written bid with a clear scope. Most bids that lose money don't fail on the math; they fail because one of those five was guessed, usually the labor hours or the overhead.
Below is the method, followed by one residential job (a 40 amp EV charger circuit) priced line by line, so you can see where every dollar of the quote comes from.
Before you bid: is this job worth bidding?
Not every request deserves a bid. Ask three questions first:
- Can your crew do it, with the license you hold? Some jobs need a master electrician to pull the permit, or a specialty you don't have.
- Can you staff it on the dates they want? A bid you win and can't staff costs more than a bid you skip.
- Is the customer comparing on scope or on price alone? A request with no drawings, no site visit and five other bidders is usually a price race.
For commercial work the scope arrives as a request for proposal (RFP) with drawings and specs. For residential work you write the scope yourself, so a site visit is part of the bid, not an extra.
Step 1: Do the material takeoff
A takeoff is the list of every material the job needs, counted from the plans or the site walk. Go room by room or circuit by circuit, and count devices, boxes, wire runs, breakers, conduit and fittings.
A few habits keep takeoffs honest:
- Measure wire runs along the real route (up, across, down), not in a straight line.
- Price from your supplier's current quote, not last year's invoice. Copper moves.
- Add a waste allowance. Ten percent is a common starting point for wire and fittings; use your own history once you have it.
Step 2: Estimate labor hours by task
Labor is where most electrical bids go wrong, because it's the number you can't buy at a counter. Split the job into tasks and give each one hours, based on how long your crew takes.
Commercial estimators often start from published labor units, such as the NECA Manual of Labor Units, then adjust them for site conditions. On residential jobs, your own past jobs are the better source. If you don't track actual hours against estimated hours yet, start now: it's the single most useful number for your next bid.
Don't forget the hours that aren't wiring: the site survey, the permit trip, the inspection visit, cleanup and travel.
Step 3: Use loaded labor cost, not the wage
Your labor cost per hour is the wage plus everything it drags along: the employer's 7.65% share of Social Security and Medicare, unemployment tax, workers' comp, insurance and paid time off. That total is called the loaded (or burdened) rate.
For scale, the US median wage for electricians was $29.98 an hour in May 2024, according to the Bureau of Labor Statistics. Your own wage and burden will differ by state and crew, so use your payroll numbers. In the example below we assume a 30% burden, which you should replace with yours.
Step 4: Add overhead per billable hour
Overhead is what it costs to keep the business open whether or not a job is running: van payments, fuel, tools, insurance, the office, software, your phone. The cleanest way to bid it is per billable hour:
- Add up a year of overhead.
- Estimate the hours you'll actually bill in that year, not the hours you'll work.
- Divide. That's your overhead per hour, and every bid carries it.
Skipping this step is how a busy contractor ends the year with no money: every job looked profitable on materials and wages alone.
Step 5: Add profit, and know if it's markup or margin
Profit is the last line, and the most misread one. Markup is a percentage of your cost. Margin is a percentage of the price. They're not the same number:
| Markup on cost | Margin on price |
|---|---|
| 10% | 9.1% |
| 15% | 13.0% |
| 20% | 16.7% |
| 25% | 20.0% |
| 33.3% | 25.0% |
If you want a 15% margin, divide your total cost by 0.85. Multiplying cost by 1.15 only gives you 13%.
A worked example: bidding an EV charger circuit
Here's one residential job taken from walkthrough to price. The customer wants a 40 amp Level 2 charger in an attached garage, 40 feet from the panel. All prices below are example inputs to show the method, not market rates; put in your own.
Two code points shape the scope. An EV charger counts as a continuous load, so the NEC sizes its circuit at 125%: a 40 amp charger needs a 50 amp circuit. And under the 2023 NEC, a 240 volt receptacle in a garage needs GFCI protection. Check which code edition your jurisdiction has adopted, and do a load calculation on the panel before you quote. If the panel can't take the new load, this is now a panel upgrade bid.
Materials (example prices):
| Item | Cost |
|---|---|
| 50 amp 2 pole GFCI breaker | $130 |
| 6/3 NM cable, 40 ft at $3.50 | $140 |
| NEMA 14-50 receptacle and box | $55 |
| Staples, connectors, cover, misc | $30 |
| 10% waste and contingency | $35.50 |
| Materials total | $390.50 |
Labor: site survey 0.5 h, cable run 3.0 h, panel work 1.0 h, device and test 0.5 h, cleanup 0.5 h, permit and inspection visit 1.0 h. Total 6.5 hours. At $29.98 plus a 30% burden, the loaded rate is about $39 an hour, so labor is $253.50.
Permit: $100 in this example. Fees vary by city, so call the building department or check its fee schedule.
Overhead: say $60,000 a year over 1,500 billable hours, which is $40 an hour. For 6.5 hours, that's $260.
| Line | Amount |
|---|---|
| Materials | $390.50 |
| Labor | $253.50 |
| Permit | $100.00 |
| Overhead | $260.00 |
| Total cost | $1,004.00 |
| Price at 15% margin (cost ÷ 0.85) | $1,181.18 |
| Quoted price, rounded | $1,185 |
The rounded quote gives a 15.3% margin, or about an 18% markup on cost. Notice that overhead ($260) is bigger than labor ($253.50). That's normal on a short job, and it's the line a gut feel price leaves out.
What to put in the written bid
A bid is a promise, so the paper matters as much as the number. Include:
- your business name, license number and contact details
- the customer, the job address and the date
- the scope in plain words: what you'll install, where, and to which code
- exclusions: patching drywall, painting, utility service changes, the charger itself if the customer supplies it
- the price, and whether permits and inspection are included
- how long the price is valid, the deposit and the payment terms
- what happens if you find something on site, such as aluminum branch wiring or a panel with no room
- a line for the customer to accept
Flat rate, time and materials or unit pricing?
Pick the pricing model to fit the job, not out of habit.
| Model | Use it when | Watch out for |
|---|---|---|
| Fixed bid | The scope is clear and you've seen the site | Hidden conditions eat your profit |
| Time and materials | Troubleshooting or old houses with unknowns | Customers want a cap; agree one in writing |
| Unit pricing | Repeated work, such as 40 identical apartments | Your unit price must include overhead |
| Flat rate book | Common service calls you do every week | Review the book when costs change |
Keep your bids in one place
When every quote lives in one system, you stop retyping prices and you can see which bids you won. In ExecCortex Invoicing you keep breakers, cable and your hourly rate as Products, then write an Estimate for a rough budget and a Quotation once the scope is fixed. Both use the same builder, templates and numbering as your invoices, and a quotation the customer agrees to is marked Accepted, so your list shows which bids you won. The solutions page for electricians shows how a call becomes a lead, then a job, then an invoice.
To be clear about the limits: it doesn't do takeoffs from drawings and it doesn't hold a labor unit library. You count and price the job as above, then enter the lines. For quoting across other trades, see estimate software for contractors, and the painting job estimate guide walks the same method through one room.
FAQ
How do electricians calculate a bid?
They add materials from a takeoff, labor hours at a loaded rate, permits, and overhead per billable hour, then add profit as a margin on the price. The steps above follow that order, and the EV charger example shows each line.
What percentage should an electrician mark up materials?
There's no single right percentage. Many contractors mark up materials separately from labor, but what matters is that the total price covers overhead and leaves the profit you planned. Check whether your target is a markup on cost or a margin on price.
How do I find electrical jobs to bid on?
Residential work mostly comes from referrals, local search and builders you already know. For commercial work, general contractors post bid invitations on plan rooms and bid boards, and public projects are listed by the city, county or state that runs them.
Should I charge for an estimate?
Many electricians give residential estimates at no cost and charge for detailed design work or a long troubleshooting visit. If you do charge, say so before the visit and credit the fee against the job if the customer hires you.
How long should a bid be valid?
Thirty days is common, and shorter when material prices are moving. Put the date on the bid, so a customer who signs three months later doesn't hold you to an old copper price.